C-Energy Planá published a press release with information that its innovation scheme regarding the combination of turbine and battery operation will be made available to other power companies in the Czech Republic. Two visible changes took place on the premises of C-Energy Planá during the past few months - a new entrance directly from Průmyslová Street was opened and the water treatment building was pulled down.

As regards development projects - a tendering procedure for a supplier of the system of electricity accummulation has been in progress. We have been preparing a call for bids for the supply of a photovoltaic power plant. The plant will be located on an unused plot between Kovosvit shuttle train rails and the railway connecting Prague and České Budějovice. 

The company responsible for the construction of the heat distribution pipeline to Planá nad Lužnicí has been waiting for the building permit and immediately after it has been in force, the company will start digging. 